Methodology lock
The calculation ground rules every figure in this cycle is computed under
FY2025 GRI report2025 (Jan 2025 - Dec 2025) · GRI-STANDARDS
Active
Computed 4 Mar 2026 at 10:12 (run 000318).
Locked values
Locked by Mei Tan on 20 Feb 2026 at 14:05
Lock completeReplace lock
GWP family
AR6
Boundary approach
Operational control
Energy convention
Net calorific value (NCV)
Calculation rule set
GHG Protocol Corporate Standard + Scope 2 Guidance
Version 1
Factor edition
2026.1
Published 10 Feb 2026 · sources DESNZ · EMA · IPCC · SEFR
Locked
20 Feb 2026 at 14:05
by Mei Tan
Compute invalidated at
20 Feb 2026 at 14:05
Boundary approach[Help text, authored at build]
Energy convention[Help text, authored at build]
State: the factor edition picker inside the lock form (opened from Replace lock; the form itself is the Lock form page)
State: the replacement confirmation, on a later day when edition 2027.0 has been published
State: the completion re-check report, shown after a lock completes or is replaced (non-blocking: the lock completes and the violating entries refuse at compute)
Re-check against edition 2026.1
1 of 48 entries needs attention
1 activity uses a unit this edition does not accept for its carrier
Tuas Cold Storage · refrigerant leakage · Mar 2025 ·
ACTIVITY_UNIT_INVALID